The U.S. back end: spent fuel, Yucca Mountain, the money, and the 2026 recycling push

The dated figures behind Module 2: how much spent fuel there is and where, what Yucca Mountain's status actually is, what the breach of the disposal contracts has cost, what the Nuclear Waste Fund holds, and where the 2026 Nuclear Lifecycle Innovation Campus program and the reprocessing rulemakings stand.

Compiled by the author for a public panel on 12 August 2026 and last re-checked on that date. Every figure below carries its own as-of date and source. Items marked ⚠ are commonly misstated; the correction is given. The site takes no position on whether the United States should recycle its spent fuel.

Inventory (as of 31 December 2022 measured; June 2025 working figure)

Yucca Mountain (status as of August 2026)

The money (as of 30 September 2025)

The breach. Under the 1982 Act’s Standard Contracts DOE was to begin taking fuel on 31 January 1998. It has accepted none. Damages are paid from the Treasury’s Judgment Fund — by taxpayers, not from the Nuclear Waste Fund — under a 2002 appellate ruling.

ItemAmountSource
Paid to utilities to date (settlements + judgments)$12.2 billionDOE FY2025 Agency Financial Report [8]
Paid in FY2025 alone$1.12 billionsame
Estimated remaining liability$38.6–44.3 billionsame
⚠ Total liability including amounts already paid$50.8–56.5 billionsame — the upper figure is often misquoted as “remaining”

DOE’s estimate assumes Congress will both appropriate funds and amend the Act to permit consolidated interim storage; if interim storage slips, the number grows.

The Nuclear Waste Fund. Ratepayers paid a fee of 0.1 cent per kilowatt-hour from 1983 until a federal court ordered collection stopped in 2013 (DOE suspended it in May 2014). The Fund’s balance at 30 September 2025 was **51.4billion∗∗,ofwhich51.4 billion**, of which 21.8 billion was fees and most of the rest Treasury interest; FY2025 income was $1.96 billion, almost entirely interest [9]. The Fund cannot be spent without appropriation and sits on-budget, where its balance offsets the deficit.

Private consolidated interim storage (status as of January 2026)

The 2026 recycling push (status as of August 2026)

Economics (prices as of 31 July 2026)

International comparison (as of August 2026)

Sources

  1. U.S. Department of Energy, FY2026 Congressional Justification, Nuclear Waste Disposal (June 2025).
  2. Pacific Northwest National Laboratory, PNNL-33938 Rev. 1.1, Spent Nuclear Fuel and Reprocessing Waste Inventory (December 2024), data at 31 December 2022.
  3. U.S. Government Accountability Office, nuclear-waste disposal key issues page and GAO-21-603 (September 2021); Nuclear Waste Technical Review Board, commercial SNF fact sheet Rev. 2.
  4. Nuclear Waste Policy Act of 1982, as amended (42 U.S.C. §§10101 ff.), §§135, 148, and the 70,000-MTHM cap; NRC backgrounder on the Yucca Mountain license review.
  5. U.S. Nuclear Regulatory Commission, NUREG-1949, Safety Evaluation Report for the Yucca Mountain application, vols. 2–5 (2014–15); In re Aiken County (D.C. Cir. 2013); NRC Chairman’s testimony, 4 March 2015.
  6. Utility Dive, “Will DOE’s nuclear lifecycle innovation campuses finally close the fuel cycle?” (2026) — quoting DOE’s acting deputy assistant secretary.
  7. Office of Sen. Rosen, release of 4 August 2026 on S. 5233.
  8. U.S. Department of Energy, FY2025 Agency Financial Report, notes 19 and 22 (December 2025).
  9. U.S. Department of Energy, Nuclear Waste Fund Annual Financial Report Summary, FY2025.
  10. Nuclear Regulatory Commission v. Texas, 605 U.S. ___ (18 June 2025); Fifth Circuit dismissals of 20 October 2025; Supreme Court order list of 12 January 2026.
  11. U.S. Department of Energy, NLIC request for information (SAM.gov, 28 January 2026) and release of 28 July 2026; Oklahoma Department of Commerce statement.
  12. 91 FR 38124 (24 June 2026) and 91 FR 38928 (26 June 2026); 10 CFR 74.51(a).
  13. Atomic Energy Act §110a; 10 CFR 70.11; DOE recycling solicitation of 22 April 2026; Executive Order 14299 §5(c).
  14. INL/RPT-23-03365 (NRC TLR-RES/DE/REB-2023-10, December 2023); ORNL/TM-2020/1751; OECD-NEA technology-readiness assessment (2019).
  15. American Nuclear Society, Nuclear Newswire, 29 May 2026.
  16. Cameco, published spot price, 31 July 2026.
  17. Bunn, Fetter, Holdren and van der Zwaan (2003).
  18. Congressional Research Service, R48364 (23 January 2025).
  19. GAO-08-483; Congressional Budget Office (2007).
  20. Japan Nuclear Fuel Limited, provisional operating plan; cost figure as reported in 2026.
  21. Three Yankees presentation to the Council of State Governments Eastern Regional Conference, 29 October 2020.
  22. National Academies (2023); Andra, Cigéo key figures; Orano, La Hague site description.
  23. STUK statement of 4 August 2026.
  24. Nuclear Decommissioning Authority (UK), 24 January 2025.
  25. Autorité de sûreté nucléaire et de radioprotection (France), plutonium inventory statements.

Compiled from the author’s panel data annex of 11 August 2026, which carries the URL for each item above.

Companion to the module. Last re-checked 2026-08-12.